PRODUKTIVITAS PEKERJA DALAM PEKERJAAN PEMASANGAN DINDING BATA DENGAN METODE CREW BALANCE CHART

Main Article Content

Eddy Putra
Hendrik Sulistio

Abstract

The determination of the magnitude of value of productivity is the first step that must be conducted to determine magnitude of increase productivity that can be applied in construction projects. The determination of value of productivity requires the completeness of data obtained from workers data collection. Data collection displayed in form of Crew Balance Chart to get unproductive time and coefficient of workers based on field conditions in the installation of brick and to increase the productivity of workers on construction project of Residential Houses Cempaka Baru. Methods of data collection using observations in the field, as well as the data processed by using simple math. From the results of the research known to time is unproductive time of workers on the job installation of brick wall construction projects Cempaka Baru on front area is 9,711%, and on back area is 48,737% so it can be called that workers in the front area is quite productive while the workers in back area tend to be not productive. The productivity of workers front area amounted to 0,98 m2/h while productivity in ideal conditions can reach 1,33 m2/h, while that for back area the productivity 1,53 m2/h while productivity ideally 2,25 m2/h.


ABSTRAK

Penentuan besarnya nilai produktivitas merupakan langkah awal yang harus dilakukan untuk mengetahui besarnya peningkatan produktivitas yang dapat diterapkan dalam proyek konstruksi. Penentuan nilai produktivitas memerlukan kelengkapan data yang didapat dari pendataan pekerja. Pendataan pekerja ini ditampilkan dalam bentuk diagram Crew Balance Chart untuk mendapatkan waktu tidak produktif dan koefisien pekerja berdasarkan kondisi lapangan dalam pekerjaan pemasangan dinding bata serta dapat meningkatan produktivitas pekerja pada proyek konstruksi Rumah Tinggal Cempaka Baru. Metode pengumpulan data dalam crew balance chart menggunakan observasi di lapangan, serta data diolah dengan menggunakan matematika sederhana. Dari hasil penelitian diketahui waktu tidak produktif pekerja pada pekerjaan pemasangan dinding bata proyek konstruksi Cempaka Baru pada area depan 9,711% dan pada area belakang 48,737% sehingga dapat dapat disebut pekerja pada area depan cukup produktif sementara pekerja pada area belakang cenderung tidak produktif. Produktivitas pekerja pada area depan sebesar 0,98 m2/jam sedangkan produktivitas dalam kondisi ideal dapat mencapai 1,33 m2/jam, sementara itu untuk area belakang produktivitasnya sebesar 1,53 m2/jam sedangkan produktivitas idealnya 2,25 m2/jam.

Article Details

Section
Articles

References

Cahyo, Andi Dwi. “Perbandingan Biaya dan Waktu pada Pelaksanaan Pekerjaan Pasangan Dinding Bata Ringan dan Dinding Bata Merah dengan Metode Time Study.” (2016).

Caroline, Denny. “Pengaruh Peningkatan Produktivitas Terhadap Durasi Fabrikasi besi Pada Proyek Indonesia 1 dengan Crew Balance Chart.” (2018).

Ervianto, W I. Manajemen Proyek Konstruksi. Yogyakarta: Andi Offset, 2005.

—. “Pengukuran Produktivitas Kelompok Pekerja Bangunan dalam Proyek Konstruksi.” (2008).

Han, F and D Leong. Productivity and Sercive Quality. Singapura: Prentice Hall, 1996.

Handayani, Sri. “Kualitas Batu Bata Merah dengan Penambahan Serbuk Gergaji.” (2010).

Herlina, Indrawati and Misbach. “Mata Kuliah Psikodiagnostik II (Observasi).” Fakultas Ilmu Pendidikan, Universitas Pendidikan Indonesia, 2007.

James J O'brien; Zilly; Robert G. Contractor's management handbook. New York: McMraw-hill inc, 1991.

Jitchaiyaphum, et al. “Cellular lightweight concrete containing high-calcium fly ash and natural zeolite.” International Journal of Minerals, Metallurgy and Materials (2013): 462.

Kristiana, Retna and Aan Pujiandi. “Analisa Produktivitas Dinding Bata Ringan Dinding Precast pada Bangunan Gedung Tinggi Hunian.” Rekayasa Sipil Vol.5 No.2 (2016): 81-92.

Kuprenas, J.A and A.S Fakhouri. A crew balance chart study improving construction productivity. management association of America, 2001.

Mania, Siti. “Observasi Sebagai Alat Evaluasi dalam Dunia Pendidikan dan Pengajaran.” Lentera Pendidikan Vol 11 No 2 (2008): 220-233.

Oxford University Press. Idea and Method of Legal Research. New Delhi: Oxford University Press, 2019.

Rustendi, Iwan. “Produktivitas Pekerjaan Pasangan Batu Bata pada Dinding Rumah Tinggal.” (2011).