ANALISIS FAKTOR-FAKTOR PENYEBAB KETERLAMBATAN PROYEK KONSTRUKSI BANGUNAN RUMAH SUSUN MAHASISWA DI PALEMBANG

Isi Artikel Utama

Kristian Ananda
Firdaus
Ely Mulyati

Abstrak

The significant increase in the number of university students every year also has an impact on the increasing housing needs of students. The construction of student flats is a form of government support in order to facilitate the housing needs. However, during the implementation of construction projects, various problems often arise, one of which is delay, where this quantitative study aims to find out what factors have a significant influence on project delays. This study involved 30 samples (14 people from project owners, 9 people from construction management consultants, and 7 implementing contractors) as research respondents selected based on the purposive sampling method. The questionnaire data that has been collected is analyzed using descriptive statistics and analytical statistics of the PLS SEM analysis model using the SmartPLS 4 program. The results showed that the most influential causative factors were contractor management with a p value (0.000 > 0.005), statistical t-value (3.581 > 1.65), quality management control with a p value (0.000 > 0.005), statistical t-value (3.883 > 1.65), site characteristics with p value (0.009 > 0.005), statistical t-value (2.357 > 1.65), owner's personality with p value (0.037 > 0.005), statistical t-value (1.790 > 1.65),  and environmental factors with a p value (0.048 > 0.005) Statistical  t-value (1.670 > 1.65).


Abstrak


Peningkatan jumlah mahasiswa perguruan tinggi yang signifikan setiap tahun berdampak juga pada meningkatnya kebutuhan hunian mahasiswa. Pembangunan rumah susun mahasiswa merupakan bentuk dukungan pemerintah dalam rangka memfasilitasi kebutuhan hunian tersebut. Namun selama pelaksanaan proyek konstruksi sering kali muncul berbagai masalah salah satunya adalah keterlambatan, dimana studi kuantitatif ini bertujuan mengetahui faktor-faktor apa saja yang memiliki pengaruh signifikan terhadap keterlambatan proyek. Penelitian ini melibatkan 30 sampel (14 orang dari pemilik proyek, 9 orang dari konsultan manajemen konstruksi, dan 7 orang kontraktor pelaksana) sebagai responden penelitian yang dipilih berdasarkan metode purposive sampling. Data kuesioner yang telah dikumpulkan dianalisis menggunakan statistik deskriptif dan statistik analitik model analisis PLS SEM menggunakan program SmartPLS 4. Hasil penelitian menunjukkan bahwa faktor penyebab yang paling berpengaruh adalah manajemen kontraktor dengan nilai p value (0,000 > 0.005) nilai t statistik (3,581 > 1,65), pengendalian manajemen mutu dengan nilai p value (0,000 > 0.005) nilai t statistik (3,883 > 1,65), karakteristik tempat dengan nilai p value (0,009 > 0.005) nilai t statistik (2,357 > 1,65), kepribadian pemilik dengan nilai p value (0,037 > 0.005) nilai t statistik (1,790 > 1,65), dan faktor lingkungan dengan nilai p value (0,048 > 0.005) nilai t statistik (1,670 > 1,65).

Rincian Artikel

Bagian
Articles

Referensi

Andi, A., Susandi, S., & Wijaya, H. (2003). On representing factors influencing time performance of shop-house constructions in Surabaya. Civil Engineering Dimension, 5(1), 7-13.

Cushman, R. F., Carter, J. D., Coppi, D. F., & Gorman, P. J. (2000). Proving and pricing construction claims. Wolters Kluwer.

Hair Jr, J. F., Hult, G. T. M., Ringle, C. M., Sarstedt, M., Danks, N. P., & Ray, S. (2021). Partial least squares structural equation modeling (PLS-SEM) using R: A workbook (p. 197). Springer Nature.

Husen, A. (2011). Manajemen proyek (edisi revisi). Yogyakarta: Andi.

Indonesia. (2018). Peraturan Presiden Republik Indonesia Nomor 100 Tahun 2018 Pembangunan Rumah Susun Khusus Pada Perguruan Tinggi dan Lembaga Pendidikan Berasrama. Lembaran Negara Republik Indonesia Tahun 2018 Nomor 191.

Kementerian Pekerjaan Umum dan Perumahan Rakyat. (2024). Overview Pembangunan Rumah Susun 2024. Direktorat Rumah Susun Direktorat Jenderal Perumahan.

Kerzner, H. (2017). Project Management: A system approach to planning, scheduling, and controlling (12th ed.) John Wiley & Sons.

Kusumastuti, A., Khorion, A. M., & Achmadi, T. A. (2020). Metode Penelitian Kuantitatif. Deepublish.

Larson, Erick W., & Gray, Clifford F. (2018). Project Management: The managerial process (7th ed). McGraw Hill.

Proboyo, B. (1999). Keterlambatan waktu pelaksanaan proyek: Klasifikasi dan peringkat dari penyebab-penyebabnya, Dimensi Teknik Sipil, 1(1), 46-58.

Project Management Institute. (2017). A Guide To The Project Management Body of Knowledge (PMBOK Guide) (6th ed.) Project Management Institute.

Setiabudhi, H., Suwono, S., Setiawan, Y. A., & Karim, S. (2025). Analisis Data Kuantitatif dengan SmartPLS 4. Borneo Novelty Publishing.

Sudjito, S. (2020). Pembangunan rumah susun sewa mahasiswa kajian tentang inkonsistensi regulasi dan implementasi, Lambung Mangkurat Law Jurnal, 5(1), 87-99.

Zaneldin, E. K. (2006). Construction claims in United Arab Emirates: Types, causes, and frequency. International Journal of Project Management, 24(5), 453-459.