PERINGKAT FAKTOR-FAKTOR YANG MEMPENGARUHI PRODUKTIVITAS TENAGA KERJA PADA PROYEK KONSTRUKSI

Main Article Content

Celine Faustine
Mega Waty

Abstract

Human resources, which can also be called labor or manpower or workforce, is one of the various factors that affect the success of the construction project. Based on that statement, an analysis of labor productivity is necessary. There are many kinds of factors that can affect labor productivity in construction projects. The purpose of this study is to determine the highest ranks of the factors affecting or influencing labor productivity in high-rise building construction projects in Jabodetabek. The quantitative research method, namely questionnaires, is the method or the technique used in this study. Furthermore, this research was analyzed using the IBM SPSS software program for validity and reliability testing and analyzed with the Relative Importance Index (RII) to determine or find out the ranking of each factor. According to the validity and reliability test results, 14 variables are declared valid and reliable. The highest-ranked factor affecting or influencing labor productivity on construction projects is work skills with an RII score or value of 0,906.


 


Abstrak


Sumber daya manusia atau yang bisa disebut juga dengan tenaga kerja adalah satu dari berbagai macam faktor yang berpengaruh terhadap keberhasilan proyek konstruksi. Berdasarkan pernyataan tersebut, maka perlu dilakukan analisis mengenai produktivitas tenaga kerja. Ada banyak macam faktor yang dapat mempengaruhi atau berpengaruh terhadap produktivitas tenaga kerja pada suatu proyek konstruksi. Tujuan dari penelitian ini adalah untuk mengetahui peringkat tertinggi dari faktor-faktor yang mempengaruhi atau berpengaruh terhadap produktivitas tenaga kerja pada proyek konstruksi gedung bertingkat tinggi di Jabodetabek. Metode penelitian kuantitatif, yaitu dengan menggunakan angket atau kuesioner merupakan metode yang dipakai pada penelitian ini. Selanjutnya penelitian ini dianalisis menggunakan program perangkat lunak IBM SPSS untuk pengujian validitas dan reliabilitas serta dianalisis dengan indeks kepentingan relatif atau Relative Importance Index (RII) untuk mengetahui peringkat tiap faktor tersebut. Berdasarkan hasil uji validitas dan reliabilitas, terdapat 14 variabel yang dinyatakan valid dan reliabel. Hasil peringkat tertinggi dari faktor-faktor yang mempengaruhi atau berpengaruh terhadap produktivitas tenaga kerja pada suatu proyek konstruksi adalah keterampilan kerja, yaitu dengan nilai RII 0,906.

Article Details

Section
Articles

References

Akadiri, P. O., Olomolaiye, P. O., & Chinyio, E. A. (2013). Multi-Criteria Evaluation Model for the Selection of Sustainable Materials for Building Projects. Automation in Construction, 30, 113–125. https://doi.org/10.1016/j.autcon.2012.10.004

Aniceto, F. J. V. (2015). Studi Faktor-Faktor Fisik yang Mempengaruhi Produktivitas Kerja Tukang pada Proyek Konstruksi di Dili, Timor - Leste [Skripsi, Universitas Atma Jaya Yogyakarta]. SAGE Knowledge. https://doi.org/10.4135/9781452229669.n3690

Chomeya, R. (2010). Quality of Psychology Test Between Likert Scale 5 and 6 Points. Journal of Social Sciences, 6(3), 399–403.

Darmayanti, E. F. (2016). Analisis Produktivitas Kerja Karyawan Dikaitkan dengan Time Management. AKUISISI, 12(2), 42–51.

Durdyev, S., Ismail, S., & Kandymov, N. (2018). Structural Equation Model of the Factors Affecting Construction Labor Productivity. Journal of Construction Engineering and Management, 144(4). https://doi.org/10.1061/(asce)co.1943-7862.0001452

El-Batreek, A. H., Ezeldin, A. S., & Elbarkouky, M. M. G. (2013). A Framework for Construction Labor Productivity Improvement in Egypt. Architectural Engineering Conference 2013, 1007–1017. https://doi.org/10.1061/9780784412909.098

El-Gohary, K. M., & Aziz, R. F. (2014). Factors Influencing Construction Labor Productivity in Egypt. Journal of Management in Engineering, 30(1), 1–9. https://doi.org/10.1061/(asce)me.1943-5479.0000168

Enshassi, A., Mohamed, S., Mustafa, Z. A., & Mayer, P. E. (2007). Factors Affecting Labour Productivity in Building Projects in the Gaza Strip. Journal of Civil Engineering and Management, 13(4), 245–254. https://doi.org/10.1080/13923730.2007.9636444

Ervianto, W. I. (2005). Manajemen Proyek Konstruksi. Andi. http://katalog.kemdikbud.go.id/index.php?p=show_detail&id=91316

Felixius, J., & Waty, M. (2021). Analisis Sisa Material dan Penyebab Utamanya pada Proyek Bangunan Rumah Tinggal. JMTS: Jurnal Mitra Teknik Sipil, 4(1), 343–352. https://doi.org/10.24912/jmts.v0i0.10393

Hanna, A. S., Russell, J. S., Nordheim, E. V., & Bruggink, M. J. (1999). Impact of Change Orders on Labor Efficiency for Electrical Construction. 125(4), 224–232.

Hernandi, Y., & Tamtana, J. S. (2020). Faktor-Faktor yang Mempengaruhi Produktivitas Pekerja pada Pelaksanaan Konstruksi Gedung Bertingkat. JMTS: Jurnal Mitra Teknik Sipil, 3(2), 299–312. https://doi.org/10.24912/jmts.v3i2.6985

Jarkas, A. M., & Bitar, C. G. (2012). Factors Affecting Construction Labor Productivity in Kuwait. Journal of Construction Engineering and Management, 138(7), 811–820. https://doi.org/10.1061/(asce)co.1943-7862.0000501

Je, K. (2014). Faktor-Faktor Yang Mempengaruhi Produktivitas Tenaga Kerja Pada Proyek Peningkatan Jalan Raja-Maunori Kabupaten Nagekeo. TEKNOSIAR Jurnal Teknik Universitas Flores, 8(2), 25–34.

Nizar, M. (2016). Analisis Faktor-Faktor Yang Mempengaruhi Produktivitas Tenaga Kerja Tukang Besi Pada PT. Wika Beton Pabrik Produk Beton Pasuruan. Iqtishoduna, 8(2), 94–127.

Oktavio, K., Dharmawan, R. K., & Nugraha, P. (2020). Survey Mengenai Faktor-Faktor yang Memengaruhi Produktivitas Pekerja pada Beberapa Proyek Konstruksi di Surabaya. Jurnal Dimensi Pratama Teknik Sipil, 9(1), 141–148.

Pratama, A. B. (2017). Faktor yang Mempengaruhi Produktivitas Tenaga Kerja Konstruksi di Bungku Kab. Morowali Sulawesi Tengah. Prosiding Seminar Nasional Hasil Penelitian & Pengabdian Kepada Masyarakat (SNP2M), 155–159.

Rini, I. P. (2019). Pengaruh Produktivitas Tenaga Kerja Terhadap Kinerja Waktu Proyek Pada Bangunan Bertingkat. Jurnal Infrastruktur, 3(2), 127–135. https://doi.org/10.35814/infrastruktur.v3i2.715

Salawati, L., & Abbas, I. (2020). Penerapan Keselamatan dan Kesehatan Kerja pada Pelaksanaan Proyek Konstruksi. Jurnal Kesehatan Cehadum, 2(2), 38–45.

Satrya, T. A., & Waty, M. (2020). Faktor-Faktor yang Mempengaruhi Produktivitas Tenaga Kerja pada Bangunan High Rise di Republik Indonesia. JMTS: Jurnal Mitra Teknik Sipil, 3(4), 1313–1326. https://doi.org/10.24912/jmts.v3i4.8366

Trisno, D., Secio, E. W., & Limanto, S. (2021). Studi Awal pada Faktor yang Mempengaruhi Produktivitas Pekerjaan Konstruksi pada Bangunan di Surabaya dan Samarinda. Jurnal Dimensi Pratama Teknik Sipil, 10(2), 33–39.

Wijayaningtyas, M., Seran, S., Mulyadi, L., & Inskandar, T. (2019). Pengaruh Faktor Eksternal dan Internal terhadap Produktivitas Tenaga Kerja Proyek Pembangunan Gedung. Seminar Nasional Infrastruktur Berkelanjutan 2019 Era Revolusi Industri 4.0 Teknik Sipil dan Perencanaan, 1–6. https://ejournal.itn.ac.id/index.php/semsina/article/download/2275/1978

Yuniati, N. H., & Utomo, C. (2012). Analisa Faktor-Faktor yang Mempengaruhi Produktivitas Tenaga Kerja Proyek Konstruksi di Surabaya. Prosiding Seminar Nasional Manajemen Teknologi XVI, 1–8.