PENERAPAN CRITICAL PATH METHOD DALAM PENJADWALAN PROYEK PEMASANGAN TANGKI STORAGE ST-1812, STUDI KASUS PADA PT. MSM
Main Article Content
Abstract
The installation of the ST-1812 storage tank aims to improve production efficiency at PT. MSM by saving costs in the use of steam from 16 hours to only 4 hours, which is used to heat the final product to temperature of 63°C according to work instructions. Critical Path Method is used to determine the optimal construction time, because this method can identify the sequence of tasks that are most critical or that have the most impact on the duration of the entire project. The purpose of this study is to determine the optimal duration for implementation and completion of the ST-1812 storage tank installation project at PT MSM. The analysis of the CPM application showed that the project took 90 days to complete, with 19 activities included in the critical path. The addition of working hours (overtime) on activities on the critical path makes the project can be completed in 73 days, 17 days faster than the initial duration of the project. The initial cost of the project was IDR 66,555,000, and the cost after accelerating the project with crashing calculations was IDR 74,886,429, with a cost slope of IDR 8,331,429.
Article Details

This work is licensed under a Creative Commons Attribution-NonCommercial-ShareAlike 4.0 International License.
All publications by Jurnal Ilmiah Teknik Indsutri (Jurnal Keilmuan Teknik dan Manajemen Industri ) [p-ISSN: 2337-5841, e-ISSN: 2355-6528] is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.
References
. A. Robiana, M.Y. Nahar, and H. Harahap, “Pemanfaatan Gliserin dari Residu Gliserin Sebagai Plasticizer untuk Pembuatan Bioplastik dengan Bahan Baku Pati Bonggol Pisang Kepok,” Jurnal Teknik Kimia USU, vol. 5, no. 4, pp. 26–32, 2016. https://doi.org/10.32734/jtk.v5i4.1551.
. P. Yuliarty, and R. Anggraini, “Construction Service Project Scheduling Analysis Using Critical Path Method (CPM), Project Evaluation and Review Technique (PERT),” International Journal of Innovative Science and Research Technology, vol. 6, no. 2, pp. 477-480, 2021.
. W. Agyei, “Project Planning and Scheduling Using PERT and CPM Techniques With Linear Programming: Case Study,” International Journal of Scientific & Technology Research, vol. 4, no. 08, pp. 222-227, 2015.
. J.R. Turner, K.V. Grude, and L. Thurloway, The Project Manager as Change Agent: Leadership, Influence and Negotiation, London, New York: McGraw-Hill, 1996.
. Project Management Institute, ed. A Guide to the Project Management Body of Knowledge: PMBOK® Guide. 5. ed. PMI Global Standard. Newtown Square, Pa: PMI, 2013.
. S. Atin, and R. Lubis, “Implementation of Critical Path Method in Project Planning and Scheduling,” IOP Conference Series: Materials Science and Engineering 662, no. 2, 2019: 022031. https://doi.org/10.1088/1757-899X/662/2/022031.
. O.U. Cynthia, “Implementation of Project Evaluation and Review Technique (PERT) and Critical Path Method (CPM): A Comparative Study,” International Journal of Industrial and Operations Research, 3, no. 1, 2020. https://doi.org/10.35840/2633-8947/6504.
. Y. Farida, and L.P. Anenda, “Network Planning Analysis on Road Construction Projects by CV. X Using Evaluation Review Technique (PERT)-Critical Path Method (CPM) and Crashing Method,” International Journal of Integrated Engineering, vol. 14, no. 4, pp. 377-390, 2022. https://doi.org/10.30880/ijie.2022.14.04.029.
. A. Tresnadi, S. Suparno, S. Sutrisno, and W. Kusdiana, “Time Acceleration Analysis and Optimal Cost of Hospital Hospital Development Project on Ship Building Using Critical Path Method (Case Study: PT. PAL Indonesia (PERSERO)),” Journal ASRO, vol. 12, no. 01, pp. 137-145, 2021. https://doi.org/10.37875/asro.v12i01.390.
. Fachrurrazi, and S. Husin, “Practical Crash Duration Estimation for Project Schedule Activities,” Journal of King Saud University - Engineering Sciences, vol. 33, no. 1 pp. 1–14, 2021. https://doi.org/10.1016/j.jksues.2019.09.005.
. K.R. Ririh, and N.Y. Hidayah, “Reducing Project Duration of An Apartment Project by Waskita Karya Using Crashing Method,” IOP Conference Series: Materials Science and Engineering 852, no. 1, 2020: 012087. https://doi.org/10.1088/1757-899X/852/1/012087.
. A. Cahyono, M.A. Titisari, and Rusdiyantoro, “Application of the FMEA Method in Determining Improvement Priorities in the Product Quality System at Company X,” Jurnal Scientia, vol. 12, no. 02, pp. 1218–1224, 2023. https://doi.org/10.58471/scientia.v12i02.1329.
. A. Angelin, and S. Ariyanti, “Analisis Penjadwalan Proyek New Product Development Menggunakan Metode PERT dan CPM,” Jurnal Ilmiah Teknik Industri, vol. 6, no. 1, pp. 63-70, 2018. https://doi.org/10.24912/jitiuntar.v6i1.3025.
. S. Zareei, “Project Scheduling for Constructing Biogas Plant Using Critical Path Method,” Renewable and Sustainable Energy Reviews, vol. 81, no. 1, pp. 756-759, 2018. https://doi.org/10.1016/j.rser.2017.08.025.
. N.M. Astari, A.M. Subagyo, and K. Kusnadi, “Perencanaan Manajemen Proyek dengan Metode CPM (Critical Path Method) dan PERT (Program Evaluation and Review Technique),” Jurnal Konstruksia, vol. 13, no. 1, pp. 164-180, 2021. https://doi.org/10.24853/jk.13.1.164-180.
. Keputusan Menteri Nomor 102, “Keputusan Menteri Tenaga Kerja dan Transmigrasi Republik Indonesia Nomor 102 Tahun 2004 Tentang Waktu Kerja Lembur dan Upah Kerja Lembur,” 2004, Sumber: https://jdih.kemnaker.go.id/katalog-289-KEPUTUSAN%20MENTERI.html [diakses 30 Juni 2024]